A multi-section custom fabricated burner assembly for a chemical plant manufactured by Kubes Steel.

Project Date: 
Wednesday, July 22, 1992 to Friday, October 2, 1992
Market: 
Material: 

Fabricated housing for a fan assembly by Kubes Steel from the early 1990's.

Project Date: 
Saturday, June 20, 1992 to Monday, July 20, 1992
Market: 
Material: 

Kubes Steel completely fabricated this Atox Mill including it's steel railing and mezzanine platform for a cement plant in Ontario.

Material: 

Custom fabricated pedestrian bridge, spanning across Spencer Creek.  The bridge rests on a series of original limestone piers dating back to the 1800s.  The bridge steel frame was custom fabricated by Kubes Steel at our Jones Road shop in 1990.

Material: 

Multi-section custom fabricated pentock for a hydro-electric power generation project.

Project Date: 
Wednesday, February 21, 1990 to Monday, May 7, 1990
Material: 

Kubes Steel manufactured 3 hydraulic turbine scroll cases as part of a power generation project in the United States.  Assembled, tested and painted by Kubes Steel.

Project Date: 
Thursday, October 1, 1987 to Friday, April 1, 1988